Siddhirganj 335MW Combined Cycle Power Plant
Client
Electricity Generation Company of Bangladesh
Category
Power Plant
Completed on

October, 2016

Location
Siddhirganj, Narayanganj
Value (BDT) in Million
1300
Value (USD) in Million
16
Project Description
Site arrangement, site development and all temporary site works.
Site clearance and sand filling works.
Construction of boundary wall.
Test pile and load tests.
Acquision procurement and installation of 50 m3 batching plant.
Soil improvement work.
Pilling work.
Foundation works.
Construction of admin and canteen, workshop and warehouse building.